Projects

Afghanistan-Hydropower Plant in Feyzabad benefits 60,000 people1 min read

25. March 2019, Reading Time: < 1 min

Afghanistan-Hydropower Plant in Feyzabad benefits 60,000 people1 min read

Lesedauer: < 1 Minute

Constructions on the hydropower plant in Feyzabad will now resume after clarifying geological circumstances, reports Wadsam, the afghan business portal.

The hydropower plant will provide electricity to Feyzabad‘s entire population – in total about 60,000 people. The Afghan-German Cooperation funds the construction via KfW Development Bank at a total cost of AFN 3.7 billion. Constructions started in 2015 and shall be finished by December 2020. The hydropower plant in Feyzabad will ensure that residents no longer have to rely on expensive and environmentally harmful diesel generators. Work to expand the municipal grid in the city of Feyzabad was completed recently. Once the new power plant is completed and connected to the municipal grid, up to 60,000 of Feyzabad‘s residents will benefit from electricity generated from renewable energy sources.

 

Share: